Hi experts.
Actually i´m accumulating costs from projects tasks to assets under construction, and i´ve done both next flows:
1. I created a PO assigned to the project task after have assigned an asset under construction to his task, and the cost was succesfully acumulated in the asset under construction.
2. I created a PO assigned to the project task before have assigned an asset under construction to his task, and the cost was not succesfully acumulated in the asset under construction. So i created a Settlement Run from Project Tasks, indicating the task i want to accumulate in the AuC, but did´nt obtained what i expected.
Does anyone knows what am i doing wrong?
Hope for you to help me.
Best regards.